In 2014 UNIHA Wasser Technologie GmbH finalized its first turn-key project in Ghana comprising four river water treatment plants in four different locations.

The scope of the project included the design, supply and installation of the water treatment equipment, civil works, power supply system and raw water intakes.

The start-up of all four plants took place on 29th of January 2014, only 18 months after contract coming in force including getting the local approvals.

The customer is highly satisfied with the rapid completion of the project as well as the excellent quality of the water treatment plants and produced water.

The plants include:

  • Raw water intake pumping 
  • Chemical dosing
  • Rapid Mixer
  • Flocculator
  • Tubesettler
  • Sandfilter
  • Disinfection
  • Treated water storage
  • Treated water pumping
  • Control system with remote service function
Treatment Plant 1000 m³/d
Treatment Plant 1000 m³/d
 
Sand Filters
Sand Filters
 
Treatment Hall 2000 m³/d
Treatment Hall 2000 m³/d